Purpose: A new 3.0 MT capacity Hot Strip Mill is under installation at RSP to meet the market requirements of higher coil weight, wider strip, higher strength grades and excellent product qualities.
Stage II Approval date & Cost: 23.04.2015; Rs. 3127 crore
Contractor (Main Package): Consortium of Mitsubishi and L&T
Present Status: Engineering almost completed and site erection activities are in progress.
Scheduled Commissioning Date: August 2018
Expected Commissioning: Jan 2020